Project Start Date: Mon 4/3/00
Project Finish Date: Thu 12/21/00
ID | Task_Name | Duration | Start_Date | Finish_Date | Predecessors | Resource_Names |
---|---|---|---|---|---|---|
1 | Planning | 35 days | Mon 4/3/00 | Fri 5/19/00 | ||
2 | Create House Plans | 7 days | Mon 4/3/00 | Tue 4/11/00 | ||
3 | Find Land | 14 days | Wed 4/12/00 | Mon 5/1/00 | 2 | |
4 | Find Contractor | 7 days | Tue 5/2/00 | Wed 5/10/00 | 3 | |
5 | Set Budget | 7 days | Thu 5/11/00 | Fri 5/19/00 | 4 | |
6 | Begin Construction | 189 days | Mon 4/3/00 | Thu 12/21/00 | ||
7 | Develop Land | 21 days | Mon 4/3/00 | Mon 5/1/00 | ||
8 | Construct House | 112 days | Tue 5/2/00 | Wed 10/4/00 | 7 | |
9 | Construct Interior | 56 days | Thu 10/5/00 | Thu 12/21/00 | 8 | |
10 | Approve Construct | 21 days | Mon 4/3/00 | Mon 5/1/00 | ||
11 | Inspect Land Development | 7 days | Mon 4/3/00 | Tue 4/11/00 | ||
12 | Inspect Construction | 7 days | Wed 4/12/00 | Thu 4/20/00 | 11 | |
13 | Inspect Interior | 7 days | Fri 4/21/00 | Mon 5/1/00 | 12 | |
14 | Finalize | 7 days | Tue 5/2/00 | Wed 5/10/00 | 13 | |
15 | Move In | 7 days | Tue 5/2/00 | Wed 5/10/00 |