WBS


Project Start Date: Mon 4/3/00
Project Finish Date: Thu 12/21/00

Task_Data

IDTask_NameDurationStart_DateFinish_DatePredecessorsResource_Names
1
Planning
35 daysMon 4/3/00Fri 5/19/00  
2
Create House Plans
7 daysMon 4/3/00Tue 4/11/00  
3
Find Land
14 daysWed 4/12/00Mon 5/1/002 
4
Find Contractor
7 daysTue 5/2/00Wed 5/10/003 
5
Set Budget
7 daysThu 5/11/00Fri 5/19/004 
6
Begin Construction
189 daysMon 4/3/00Thu 12/21/00  
7
Develop Land
21 daysMon 4/3/00Mon 5/1/00  
8
Construct House
112 daysTue 5/2/00Wed 10/4/007 
9
Construct Interior
56 daysThu 10/5/00Thu 12/21/008 
10
Approve Construct
21 daysMon 4/3/00Mon 5/1/00  
11
Inspect Land Development
7 daysMon 4/3/00Tue 4/11/00  
12
Inspect Construction
7 daysWed 4/12/00Thu 4/20/0011 
13
Inspect Interior
7 daysFri 4/21/00Mon 5/1/0012 
14
Finalize
7 daysTue 5/2/00Wed 5/10/0013 
15
Move In
7 daysTue 5/2/00Wed 5/10/00